This is an overview of the DRS Futures project updates as of end of June 2024. For the full update, please visit the Monthly Reports page.
Current Project Status:
- The team has finalized contract negotiations with the selected vendor
 - The engagement with the vendor on the implementation of the selected product will begin in late summer / early fall 2024
 - Finalized development of LTS data transformation pipelines in preparation for content and metadata migration
 - Completed preliminary analysis of IAM integration pathways in collaboration with IAM team
 - Continued planning, prioritization and design for integration components that will be developed by LTS team
 
Next Up:
- Work on testing plan for software implementation and testing phase
 - Plan for for agent identity management in the new system using IAM data and ORCID integration
 - Continue analysis of IAM integration pathways in collaboration with IAM team
 - Continue planning and design for integration components that will be developed by LTS team
 - Plan the implementation phase kick-off activities