This is an overview of the DRS Futures project updates as of end of November 2025.
Current Project Status:
- Initial review of migration plan completed – amendments pending
- Collections Interface specification delivered
- DRS Downstream Pipeline workflows have been finalized
- Made progress on development of Harvard tooling for ingestion
- Successful demo of end-to-end messaging pipeline
Next Up:
- Joint review and acceptance of migration plan timeline and milestones
- Joint review and acceptance of Collections Interface implementation plan and milestones
- Finalize APIs for migration tooling
- Complete development of DRS Downstream Pipeline
- Complete development of Harvard tooling for ingestion