This is an overview of the DRS Futures project updates as of end of September 2024. For the full update, please visit the Monthly Reports page.
Current Project Status:
- Finalized governance structure for Implementation Phase
- Approved and confirmed initial release of new platform in QA and Production environment and performed internal testing
- Held onsite workshops for ingestion package design
- Finalized initial data transformation pipelines for future migration
- Continued planning, prioritization and design for integration components that are being developed by LTS team
Next Up:
- Inaugural meeting of the Pilot Partners Group and Implementation Governance Board in early October
- Ingestion package design workshops with the vendor in early October
- Testing of the new platform
- Sessions with high volume depositors to discuss workflow transition plan