This is an overview of the DRS Futures project updates as of end of June 2024. For the full update, please visit the Monthly Reports page.

Current Project Status:

  • The team has finalized contract negotiations with the selected vendor
  • The engagement with the vendor on the implementation of the selected product will begin in late summer / early fall 2024
  • Finalized development of LTS data transformation pipelines in preparation for content and metadata migration
  • Completed preliminary analysis of IAM integration pathways in collaboration with IAM team
  • Continued planning, prioritization and design for integration components that will be developed by LTS team

Next Up:

  • Work on testing plan for software implementation and testing phase
  • Plan for for agent identity management in the new system using IAM data and ORCID integration
  • Continue analysis of IAM integration pathways in collaboration with IAM team
  • Continue planning and design for integration components that will be developed by LTS team
  • Plan the implementation phase kick-off activities